|
VERNON POWER AND LIGHT
Vernon, California
Vernon Power and Light had a 30,000-gallon diesel fuel release from an aboveground storage tank. Due to the sandy soils, the diesel moved quickly and traveled downward 40 feet below ground surface to a confining layer. At that depth, the diesel began moving laterally. Remedial Construction Services, L.P. (RECON) was retained on a "fast-track" contract to install a recovery trench around the perimeter of the diesel plume in effort to recover the free-phase diesel.
Recovery Trench The recovery trench was installed to a depth of 40 feet below grade. Lateral perforated piping was placed in the bottom of the trench, along with vertical risers set on 30-foot centers.
A groundwater treatment system was installed in combination with the recovery trench. This system included vacuum extraction, an oil/water separator and carbon treatment. Approximately 2,000 gallons of free-phase diesel was recovered and recycled, and an additional 200,000 gallons of water was treated in the groundwater treatment system and released into the sanitary sewer system.
Dig and Haul As part of the remedial action. RECON excavated the highly saturated soils. Approximately 5,000 tons of diesel-impacted soil was excavated and transported offsite to a licensed soil recycling facility.
After removal of the impacted soils, the base of the excavation was backfilled with permeable gravel. Water injection lines were installed to enhance the hydraulic conditions and accelerate the free product recovery. The remaining balance of the excavation was backfilled with previously excavated "clean" soil and imported backfill.
|